Enable the gantt chart summary function

This article explains the summary function of the gantt chart.

When the Process Summary function is enabled, the "Start Date" is automatically set to the earliest start date of all sub projects. Similarly, the "End Date" will automatically be set to the latest end date of all sub projects.

*This function is granted differently depending on the subscription plan. Please contact us if you wish to use this function.

1. Click on [Gantt Chart] of the project.

Screenshot 2567-03-08 at 18.30.36.png

 

2. Enter "start/end date" or "start/end actual date" of sub project

Screenshot 2567-03-08 at 18.35.08.png

 

3. Click on "Settings"

Screenshot 2567-03-08 at 18.35.43.png

 

4. Click on the Enable "Summary Function" button

Since the project period is automatically updated when the summary function is enabled, we recommend backing up the data with the data export function before enabling the summary function if you want to keep the data before the update.

Screenshot 2567-03-08 at 18.43.27.png

 

5. Automatic aggregation of time periods

The "Start Date" is automatically set to the earliest start date of all sub projects. Similarly, the "End Date" will automatically be set to the latest end date of all sub projects.

Screenshot 2567-03-08 at 18.44.56.png

 

6. Automatic tabulation when adding or updating sub projects

Screenshot 2567-03-08 at 18.46.34.png

 

Points to note

When the summary function of the process chart is enabled, the "Start/end date" or "Start/end actual date" of the tabulated sub projects cannot be edited.

Please edit the "Start/End Date" or "Start/End Actual Date" of the sub projects.

Screenshot 2567-03-08 at 18.47.53.png